Maintenance Planning & Scheduling Upgrade

Maintenance Planning & Scheduling Upgrade

Industry: Mining

Client Situation

Schedule compliance was low, planners were overwhelmed with reactive work, and weekly schedules were frequently disrupted.

Challenges

  • Poor backlog prioritization
  • Inaccurate job plans
  • No frozen weekly schedule
  • Limited communication between maintenance and operations

Approach & Methodology

  • Improved backlog prioritization rules
  • Rebuilt job plans with accurate durations
  • Implemented frozen weekly schedule
  • Trained planners and supervisors

Key Deliverables

  • Planning standards
  • Scheduling process
  • Updated job plans
  • Training materials

Results & Impact

  • Schedule compliance significantly improved
  • Reduced reactive work
  • Better coordination between teams
  • More predictable weekly execution